Abstract:
The Port of Portland is currently looking for consultants to develop designs for the Troutdale
Reynolds Industrial Park (TRIP). CA3D Consultants provides experience from many engineering
disciplines and would meet the client’s expectations. Our proposal includes the extension of
Swigert Way to Graham Road, construction of office/manufacturing building space, mitigation of
existing wetlands, and considerations for contaminated soils and groundwater. Design will
consider sustainability and preserving the natural atmosphere of the site. Completion of the
project will take into account future growth and potential land development within the area.
Figure 1. Aerial view of project site.
Land Development
Two new parcels will be created from subdividing the eastern portion of Lot 6. Lot 6a will be 4.4
acres and be bounded by Swigert Road to the north and east and the high pressure gas line to
the south. Lot 6b will be 6.5 acres and be bounded by the high pressure gas line on the north
side, Graham road on the south, and Swigert Road to the east.
The current